Week 12

On April.22, each team did a 5-minutes presentation showing where they are. After the critique on our instruction card, we need to add some slogans to it so visitors can easily get what kind of experience is in the dome. We also tested our video using the projector in the dome for the final round testing, the side voice has a bit echo but it’s ok, it might get better with the speaker on Earth Day. Before Earth Day, we need to have everything finalized, including finalize the video with water sound, finalize both poster and instruction guide stand. Then, we talked about Earth Day schedule and transportation, we need to be there around 9 a.m. and set up our dome and projector. This week will be very productive and we are getting ready for Earth Day!